Find the path that drives a toy schedule

Identify which dependency branch determines the earliest finish under explicit assumptions.

This identifies the finish-driving path in a complete toy network, beyond describing a dependency handoff.

Opens the current invite-request page. Access is subject to approval; this example is not imported automatically.

Original worked case · Manual planning resource

Inspect the decision, not just the summary.

Start with the invented evidence, follow the reasoning, and retain its limits when adapting the brief.

01 · Inspect the inputs

Every record stays visible

Inspect the invented case records
ActivityDuration in model daysPredecessor
Brief2Start
Artwork4Brief
Data preparation3Start
Assembly1Artwork and data

Use horizontal scrolling for wide tables. These records are invented, not customer data.

02 · Follow the reasoning

How the case leads to a decision

Branch A reaches the merge after 2+4=6 days; B after three. Assembly starts at max(6,3)=6 and finishes at day seven.

The bounded result

With independent resources and all inputs ready at day zero, branch A drives the seven-day earliest finish. Shortening branch B alone does not shorten that finish.

Definitions and method context

Records, decisions and policies are original synthetic examples. External references supply context; they do not validate these cases or TeamBoostAI capabilities.

GAO Schedule Assessment Guide ↗
General schedule-model context. All records, local policies and arithmetic are original toy examples, not a certified or optimized schedule.

External references checked 6 October 2026. Demand for these topics has not been measured.

Decision desk

Decide before adding more work

Decision to make: With independent resources and all inputs ready at day zero, branch A drives the seven-day earliest finish. Shortening branch B alone does not shorten that finish.

Synthetic planning case: A toy production network has branch A: brief two days then artwork four; branch B: data preparation three days. Both branches must finish before one day of final assembly.

01

Verify the network edges

Owner role · Planning owner

Evidence: Assembly requires both completed branches, with no missing input edges.

02

Compare branch lengths

Owner role · Scheduler

Evidence: Six days to artwork exceeds three days to data under the supplied durations.

03

Target the driving condition

Owner role · Delivery lead

Evidence: Any finish-shortening proposal changes the six-day branch or assembly, with resources rechecked.

Filled manual planning note

Invented planning text. Adapt it to your evidence and confirmed owners.

With independent resources and all inputs ready at day zero, branch A drives the seven-day earliest finish. Shortening branch B alone does not shorten that finish. Branch A reaches the merge after 2+4=6 days; B after three. Assembly starts at max(6,3)=6 and finishes at day seven. Resource contention, missing dependencies and duration uncertainty are excluded. A model earliest finish is not a promised date.

Questions about this workflow

Why not add both branches?

They are parallel with separate resources in this example; the merge waits for the later branch.

Does seven days predict actual delivery?

No. It is a deterministic result of invented durations, complete inputs and the stated resource assumptions.

Does this create tasks in the product?

No. The brief is a manual planning resource. Use the product access link to check onboarding and the workflows available in your account.

Put the outline to work

  1. Verify the network edges. Check: Assembly requires both completed branches, with no missing input edges.
  2. Compare branch lengths. Check: Six days to artwork exceeds three days to data under the supplied durations.
  3. Target the driving condition. Check: Any finish-shortening proposal changes the six-day branch or assembly, with resources rechecked.

From a useful outline to team work

Explore TeamBoostAI for your team

Use the owned checks and downloaded brief to discuss this planning decision alongside your TeamBoostAI tasks. Confirm available fields, roles and account features separately. The example is manual; it does not calculate live analytics, create work or run an experiment in the product. Confirm the workflows available in your account before adopting this outline.