Data ready at day 4
- Rationale and evidence
- Assembly waits until day 6
- Revisit condition
- Recheck if either input or gate changes
Dependency schedules / Delivery leads, planning owners and acceptance reviewers
Decision ledgerIdentify how much delay a non-driving branch can absorb under a fixed network model.
The decision sets a specific permissible-delay boundary for one nondriving branch.
Opens the current invite-request page. Access is subject to approval; this example is not imported automatically.
Original worked case · Manual planning resource
Start with the invented evidence, follow the reasoning, and retain its limits when adapting the brief.
01 · Inspect the inputs
| Branch or gate | Earliest ready day | Required by |
|---|---|---|
| Design | 6 | Assembly start at 6 |
| Data | 4 | Assembly start at 6 |
| Assembly | 7 finish | Both inputs ready |
Use horizontal scrolling for wide tables. These records are invented, not customer data.
02 · Follow the reasoning
The merge is driven by day six. Data can move from day four to day six: two days of model float; a three-day delay would make it ready at seven and push final finish to eight.
The data branch has two model days of available delay before it would push assembly beyond day six. Keep that float conditional on the unchanged network.
Records, decisions and policies are original synthetic examples. External references supply context; they do not validate these cases or TeamBoostAI capabilities.
GAO Schedule Assessment Guide ↗
General schedule-model context. All records, local policies and arithmetic are original toy examples, not a certified or optimized schedule.
External references checked 6 October 2026. Demand for these topics has not been measured.
Synthetic planning case: A six-day design branch and a four-day data branch feed a one-day assembly. The complete toy model has independent resources and a common start.
Decision to make: The data branch has two model days of available delay before it would push assembly beyond day six. Keep that float conditional on the unchanged network.
Owner role · Receiving owner
Evidence: Assembly requires both complete inputs.
Owner role · Scheduler
Evidence: Day six minus day four leaves two model days under the unchanged network.
Owner role · Project lead
Evidence: Any data delay above two days reopens the finish decision.
Invented planning text. Adapt it to your evidence and confirmed owners.
The data branch has two model days of available delay before it would push assembly beyond day six. Keep that float conditional on the unchanged network. The merge is driven by day six. Data can move from day four to day six: two days of model float; a three-day delay would make it ready at seven and push final finish to eight. The float belongs to this complete deterministic model. A changed resource calendar or edge can alter it.
No. It is conditional schedule allowance, not extra people or permission to omit work.
Not independently. Recalculate the full affected network after changes.
No. The brief is a manual planning resource. Use the product access link to check onboarding and the workflows available in your account.
From a useful outline to team work
Use the owned checks and downloaded brief to discuss this planning decision alongside your TeamBoostAI tasks. Confirm available fields, roles and account features separately. The example is manual; it does not calculate live analytics, create work or run an experiment in the product. Confirm the workflows available in your account before adopting this outline.
Opens the current invite-request page. Access is subject to approval; this example is not imported automatically.