Inspect a branch's available schedule float

Identify how much delay a non-driving branch can absorb under a fixed network model.

The decision sets a specific permissible-delay boundary for one nondriving branch.

Opens the current invite-request page. Access is subject to approval; this example is not imported automatically.

Original worked case · Manual planning resource

Inspect the decision, not just the summary.

Start with the invented evidence, follow the reasoning, and retain its limits when adapting the brief.

01 · Inspect the inputs

Every record stays visible

Inspect the invented case records
Branch or gateEarliest ready dayRequired by
Design6Assembly start at 6
Data4Assembly start at 6
Assembly7 finishBoth inputs ready

Use horizontal scrolling for wide tables. These records are invented, not customer data.

02 · Follow the reasoning

How the case leads to a decision

The merge is driven by day six. Data can move from day four to day six: two days of model float; a three-day delay would make it ready at seven and push final finish to eight.

The bounded result

The data branch has two model days of available delay before it would push assembly beyond day six. Keep that float conditional on the unchanged network.

Definitions and method context

Records, decisions and policies are original synthetic examples. External references supply context; they do not validate these cases or TeamBoostAI capabilities.

GAO Schedule Assessment Guide ↗
General schedule-model context. All records, local policies and arithmetic are original toy examples, not a certified or optimized schedule.

External references checked 6 October 2026. Demand for these topics has not been measured.

Keep the reason with the decision

Illustrative decision record

Synthetic planning case: A six-day design branch and a four-day data branch feed a one-day assembly. The complete toy model has independent resources and a common start.

Decision 01

Data ready at day 4

Rationale and evidence
Assembly waits until day 6
Revisit condition
Recheck if either input or gate changes
Decision 02

Up to two-day data delay

Rationale and evidence
Does not move the merge beyond day 6
Revisit condition
Recheck resource availability
Decision 03

Three-day data delay

Rationale and evidence
Data then drives a day-7 merge
Revisit condition
Replan final finish to day 8 or change assumptions

Decision to make: The data branch has two model days of available delay before it would push assembly beyond day six. Keep that float conditional on the unchanged network.

01

Confirm the merge criterion

Owner role · Receiving owner

Evidence: Assembly requires both complete inputs.

02

Calculate the allowable branch delay

Owner role · Scheduler

Evidence: Day six minus day four leaves two model days under the unchanged network.

03

Record the float-consuming change

Owner role · Project lead

Evidence: Any data delay above two days reopens the finish decision.

Filled manual planning note

Invented planning text. Adapt it to your evidence and confirmed owners.

The data branch has two model days of available delay before it would push assembly beyond day six. Keep that float conditional on the unchanged network. The merge is driven by day six. Data can move from day four to day six: two days of model float; a three-day delay would make it ready at seven and push final finish to eight. The float belongs to this complete deterministic model. A changed resource calendar or edge can alter it.

Put the outline to work

  1. Confirm the merge criterion. Check: Assembly requires both complete inputs.
  2. Calculate the allowable branch delay. Check: Day six minus day four leaves two model days under the unchanged network.
  3. Record the float-consuming change. Check: Any data delay above two days reopens the finish decision.

Questions about this workflow

Is float free capacity?

No. It is conditional schedule allowance, not extra people or permission to omit work.

Can several downstream edits each spend the same float?

Not independently. Recalculate the full affected network after changes.

Does this create tasks in the product?

No. The brief is a manual planning resource. Use the product access link to check onboarding and the workflows available in your account.

From a useful outline to team work

Explore TeamBoostAI for your team

Use the owned checks and downloaded brief to discuss this planning decision alongside your TeamBoostAI tasks. Confirm available fields, roles and account features separately. The example is manual; it does not calculate live analytics, create work or run an experiment in the product. Confirm the workflows available in your account before adopting this outline.