  "example_kind": "original synthetic manual planning case",
  "slug": "capacity-day-to-hour-conversion",
  "title": "Convert capacity days with an explicit hours rule",
  "scenario": "Synthetic planning case: A draft allocates two availability days to a review. The agreed convention is five available review-hours per day, while the request needs twelve hours.",
  "layout": "allocation",
  "dataset": {
    "heading": "Inspect the invented case records",
    "headers": [
      "Planning input",
      "Value",
      "Convention"
    ],
    "rows": [
      [
        "Available days",
        "2",
        "Availability days, not calendar duration"
      ],
      [
        "Hours per availability day",
        "5",
        "Supplied local rule"
      ],
      [
        "Requested review work",
        "12 hours",
        "Same review pool"
      ]
    ]
  },
  "derivation": "2×5=10 available review-hours; 12−10=2 hours excess. An eight-hour day must not be substituted without changing the declared availability rule.",
  "result": "Under this convention, two days provide ten review-hours and the request exceeds that by two. Retain the five-hour conversion rule with the plan.",
  "boundary": "The artifact audits planning-unit conversion, separate from product display formatting or elapsed cycle-time clocks.",
  "limitations": "A conversion rule does not prove actual effort or account for skill constraints. Preserve the original quantity and its convention.",
  "sources": [
    "schedule"
  ],
  "tasks": [
    [
      "Recover the day convention",
      "Capacity owner",
      "An availability day means five review-hours in this plan."
    ],
    [
      "Convert before comparison",
      "Planner",
      "The two-day allocation is ten review-hours, not an assumed sixteen."
    ],
    [
      "Resolve the difference",
      "Review lead",
      "The two-hour gap is assigned a scope or capacity decision."
    ]
  ],
  "faqs": [
    [
      "Does this define a company working day?",
      "No. It is the supplied available-review-time convention for the example."
    ],
    [
      "Can calendar days be used as effort days?",
      "Not automatically. Calendar duration, available time and actual effort are different quantities."
    ]
  ],
  "method_references": [
    {
      "id": "schedule",
      "title": "GAO Schedule Assessment Guide",
      "url": "https://www.gao.gov/products/gao-16-89g",
      "scope": "General schedule-model context. All records, local policies and arithmetic are original toy examples, not a certified or optimized schedule."
    }
  ]
}