Freeze the calendar rule
Owner role · Coordinator
Evidence: Weekdays, hours, timezone and holiday treatment are explicitly supplied.
Reporting decisions / Delivery leads and report reviewers
Drafting workbenchDefine a business-window duration separately from elapsed cycle time using a stated calendar and example interval.
A supplied work window can change a descriptive duration; it does not measure person effort or prove a company holiday calendar.
Opens the current invite-request page. Access is subject to approval; this example is not imported automatically.
Synthetic case: Work starts Friday 16:00 and finishes Monday 10:00 UTC. The invented calendar counts Monday–Friday 09:00–17:00 with no holidays in this interval.
Owner role · Coordinator
Evidence: Weekdays, hours, timezone and holiday treatment are explicitly supplied.
Owner role · Reviewer
Evidence: Friday 1h + Monday 1h = 2h, with 66 elapsed hours retained.
Owner role · Report owner
Evidence: Neither elapsed nor business-window duration is called hands-on effort.
Decision to make: Report 66 elapsed hours and 2 hours inside the supplied business windows as distinct measures.
Use the downloaded brief as planning input. AI suggestions remain proposals; review scope, owners and acceptance evidence yourself.
Invented planning text. Adapt it to your evidence and confirmed owners.
Clock note: 66 elapsed hours; 2 hours intersect the stated weekday 09:00–17:00 UTC windows. Effort is unknown.
From a useful outline to team work
Bring this manual reporting policy and its owned checks into your TeamBoostAI work discussion. Native report/export fields and historical reconstruction depend on your account and implementation; this worksheet does not import or change product records. Confirm the workflows available in your account before adopting this outline.
Opens the current invite-request page. Access is subject to approval; this example is not imported automatically.
A practical decision workshop
Trace an invented case, preserve the evidence limits, then adapt the manual worksheet to your own decision.
Evidence dependency diagram
Scroll the diagram sideways if needed; every dependency is also written below.
Synthetic example · not customer data
| Segment | Selected window | Included duration |
|---|---|---|
| Friday | 16:00–17:00 | 1 business-window hour |
| Weekend | Outside supplied windows | 0 business-window hours |
| Monday | 09:00–10:00 | 1 business-window hour |
Wide tables scroll sideways on small screens.
Download records (.csv) · Download complete decision kit (.json)
Decision explorer
This returns a written example explanation. It does not inspect your records or approve a real report.
Version comparison viewer
Draft: the task took 2 hours.
Clock note: 66 elapsed hours; 2 hours intersect the stated weekday 09:00–17:00 UTC windows. Effort is unknown.
| Review boundary | Draft to review | Revised example |
|---|---|---|
| Measure | Unlabelled 2 hours | Separate elapsed 66h and business-window 2h |
| Calendar | Assumed standard schedule | Explicit supplied UTC window rule |
Wide tables scroll sideways on small screens.
Friday 16:00 to Monday 10:00 is two full days plus 18 hours. The example uses UTC.
No. They measure overlap with a supplied calendar, not observed hands-on effort.
No. The brief is a manual planning resource. Use the product access link to check onboarding and the workflows available in your account.