Elapsed duration and business-window duration

Define a business-window duration separately from elapsed cycle time using a stated calendar and example interval.

A supplied work window can change a descriptive duration; it does not measure person effort or prove a company holiday calendar.

Opens the current invite-request page. Access is subject to approval; this example is not imported automatically.

Prepare a brief for human review

Drafting workbench

Synthetic case: Work starts Friday 16:00 and finishes Monday 10:00 UTC. The invented calendar counts Monday–Friday 09:00–17:00 with no holidays in this interval.

01

Freeze the calendar rule

Owner role · Coordinator

Evidence: Weekdays, hours, timezone and holiday treatment are explicitly supplied.

02

Intersect the interval with windows

Owner role · Reviewer

Evidence: Friday 1h + Monday 1h = 2h, with 66 elapsed hours retained.

03

Label both measures

Owner role · Report owner

Evidence: Neither elapsed nor business-window duration is called hands-on effort.

Decision to make: Report 66 elapsed hours and 2 hours inside the supplied business windows as distinct measures.

Use the downloaded brief as planning input. AI suggestions remain proposals; review scope, owners and acceptance evidence yourself.

Filled review note

Invented planning text. Adapt it to your evidence and confirmed owners.

Clock note: 66 elapsed hours; 2 hours intersect the stated weekday 09:00–17:00 UTC windows. Effort is unknown.

Put the outline to work

  1. State timezone and calendar rather than assuming a standard workweek.
  2. Calculate elapsed span separately from overlap with allowed windows.
  3. Version calendar changes and keep the two units labelled.

From a useful outline to team work

Explore TeamBoostAI for your team

Bring this manual reporting policy and its owned checks into your TeamBoostAI work discussion. Native report/export fields and historical reconstruction depend on your account and implementation; this worksheet does not import or change product records. Confirm the workflows available in your account before adopting this outline.

Request TeamBoostAI access

Opens the current invite-request page. Access is subject to approval; this example is not imported automatically.

A practical decision workshop

Inspect the example before choosing a rule

Trace an invented case, preserve the evidence limits, then adapt the manual worksheet to your own decision.

Evidence dependency diagram

What must be known first?

Example evidence dependenciesObserved interval leads to Two labelled clocks: elapsed span. Supplied calendar leads to Two labelled clocks: window intersections.Observed intervalSupplied calendarTwo labelled clocks

Scroll the diagram sideways if needed; every dependency is also written below.

  • Observed interval → Two labelled clocks: elapsed span.
  • Supplied calendar → Two labelled clocks: window intersections.

Synthetic example · not customer data

Inspect the records

Synthetic reporting records
SegmentSelected windowIncluded duration
Friday16:00–17:001 business-window hour
WeekendOutside supplied windows0 business-window hours
Monday09:00–10:001 business-window hour

Wide tables scroll sideways on small screens.

Download records (.csv) · Download complete decision kit (.json)

Decision explorer

Choose an evidence situation

This returns a written example explanation. It does not inspect your records or approve a real report.

Choose a situation to read its example explanation.
Read every situation without the interactive tool
Actual interval and calendar are supplied
Show both labelled measures using that calendar.
Calendar exceptions or timezone are missing
Hold the business-window value until the calendar is known.
The desired measure is hands-on effort
Collect effort evidence separately; neither clock supplies it.

Version comparison viewer

Keep the draft and its correction visible

Draft or earlier version · review its limits

Draft: the task took 2 hours.

Revised example · limits retained

Clock note: 66 elapsed hours; 2 hours intersect the stated weekday 09:00–17:00 UTC windows. Effort is unknown.

What the review changes
Review boundaryDraft to reviewRevised example
MeasureUnlabelled 2 hoursSeparate elapsed 66h and business-window 2h
CalendarAssumed standard scheduleExplicit supplied UTC window rule

Wide tables scroll sideways on small screens.

Questions about this workflow

Why is elapsed time 66 hours?

Friday 16:00 to Monday 10:00 is two full days plus 18 hours. The example uses UTC.

Do two business-window hours mean two hours of work?

No. They measure overlap with a supplied calendar, not observed hands-on effort.

Does this create tasks in the product?

No. The brief is a manual planning resource. Use the product access link to check onboarding and the workflows available in your account.